When do you need a DG synchronization panel?

A synchronization panel lets two or more generators, or generators and the grid, run in parallel and share load. It is the right choice when one DG is not enough or cannot be allowed to fail.

You need one when

  • The plant load is larger than one DG set and several sets must share it.
  • You want redundancy (N+1), so one set can be serviced while the others carry the load.
  • Load varies widely and you want sets to start and stop automatically to save fuel.
  • You need no-break changeover between grid and DG (requires DISCOM approval and grid-protection relays).

What is inside

PartPurpose
Motorised ACB per DGConnects each set to the common bus
Synchronising & load-sharing controllerMatches voltage, frequency and phase, then shares kW and kVAr
Check-synchronising relay (25)Blocks closing if the sets are out of phase
ProtectionsReverse power (32), over/under voltage and frequency, over-current, earth fault
Load managementAuto start/stop by load, priority tripping of non-essential feeders

What to send us for a quote

  • Number and kVA rating of DG sets, make of engine and alternator
  • Whether grid parallel operation is required
  • Outgoing feeders and any load-shedding priority

DG synchronization panels

One-stop service

Have a requirement? Send us the SLD or BOQ.

Our engineers reply with a costed offer within one working day — panels, bus ducts or the full HT & LT turnkey scope.

Email us WhatsApp a requirement ↑