PCC vs MCC panel: what is the difference?

Both are LT switchboards built to IEC 61439, but they do different jobs in a plant. Choosing the right one decides cost, space and how easily you can maintain the system.

A Power Control Centre (PCC) is the main LT switchboard. It receives power from the transformer and the DG set and distributes it to the rest of the plant. A Motor Control Centre (MCC) sits downstream of the PCC and starts, stops and protects individual motors.

PCCMCC
Main jobReceive and distribute bulk powerControl and protect motors
Typical incomerACB from transformer and DG, often with bus couplerACB or MCCB fed from the PCC
Outgoing feedersACB / MCCB feeders to MCCs, PDBs, APFCDOL, star-delta, soft-starter and VFD feeders
Key devicesBreakers, multifunction meters, protection relays, changeover interlocksMCCB or MPCB, contactors, overload relays, push buttons, indication
ConstructionFixed or draw-out ACBs, heavy busbar systemFixed or draw-out feeder modules, Form 3b / 4 separation

When one panel can do both

In smaller plants the PCC and MCC are often combined in one board (a PMCC). This saves space and cost, but a fault or shutdown on one section can affect the whole board, so larger and continuous-process plants usually keep them separate.

What to send us for a quote

  • Single line diagram (SLD) or load list with motor ratings and starter type
  • Transformer and DG ratings, fault level
  • Preferred breaker make (ABB, Schneider, Siemens, L&T and others)
  • Indoor / outdoor, IP rating, cable entry (top or bottom)

PCC panels · MCC panels

One-stop service

Have a requirement? Send us the SLD or BOQ.

Our engineers reply with a costed offer within one working day — panels, bus ducts or the full HT & LT turnkey scope.

Email us WhatsApp a requirement ↑